ON SITE CONSTRUCTION INFORMATION PAGE

Personnel Real Time Navigation Page

12B OTUNBA IDOWU STREET - 2ND FLOOR REFURB
PROJECT NAME:
2ND FLOOR OFFICE REFURBISHMENT
ADDRESS:
12B OTUNBA IDOWU STREET
APPROVAL NUMBER:
LSC61785
SUPERVISOR:
ARC YEMI ALADE
OFFICER:
ENG BIDEMI SAVAGE
CONSTRUCTION START DATE:
02.06.2017
CONSTRUCTION END DATE:
01.01.2019
CONTRAVENTIONS:
3 Nos. SEE JOB DETAIL
3 REMI ADEKOYA AVENUE - 10 FLATS
PROJECT NAME:
DEVELOPMENT OF 10 FLATS ON 3 FLOORS.
ADDRESS:
3 REMI ADEKOYA AVENUE
APPROVAL NUMBER:
LSC12345
SUPERVISOR:
ARC TOYE OGUNBIYI
OFFICER:
ENG NIYI ELEME
CONSTRUCTION START DATE:
01.01.2018
CONSTRUCTION END DATE:
ONGOING
CONTRAVENTIONS:
ACTIVE STOP WORK ORDER
21 REV ALLEN LANE - 4NOS TOWNHOUSES
PROJECT NAME:
4NOS TOWNHOUSES
ADDRESS:
21 REV ALLEN LANE
APPROVAL NUMBER:
LSC645272
SUPERVISOR:
ARC DEJI ALADE
OFFICER:
ENG SANMI OKI
CONSTRUCTION START DATE:
17.09.2017
CONSTRUCTION END DATE:
17.09.2018
CONTRAVENTIONS:
NONE