DEVELOPMENT OF 10 FLATS ON 3 FLOORS

PROJECT DIARY

4

PROJECT DETAILS

Project Name

Development of 10 Flats on 3 Floors

Adresss

3 Remi Adekoye Avenue

Approval number

LSC12345

Supervisor

Arc. Toye Ogunbiyi

Officer

Eng. Niyi Eleme

Start Dare

1 January 2018

End Dare

Ongoing

Contraventions

Active Stop Work Order

APPROVAL ORDER

Land Use Class

Residential

Development Density

Max 30Units / Hectare.

Set Backs

9m to Front; 5m to Sides; 5m to Rear. 6m In-Between 2 Buildings

Set Back to Public Utilities

Road: 24m Right of Way: 12m Set Back from Center of Road to Property Line

Electric Line – 11kV: 6m

Building Coverage

Maximum 50% Building Footprint

Minimum 10% Soft Landscaping

Car Parking

20nos Car Parking Spaces

ON-SITE TEAM

Contractor

Precision Builders

Architect

Design Facility

Structural Engineer

Props Nig Ltd

M&E Engineer

Pipes & Circuits Nigeria Ltd

Quantity Surveyor

Billd Nig Ltd

Project Manager

Timelines Nig Ltd

SITE ENFORCEMENT ACTION: 22.07.19

Stop work order issued! Building control were not invited for inspection prior to casting the slab. 

SITE VISIT REPORT: 16.05.19

Reinforcement placed on grid lines 4-8 and contractor advised to invite officials for inspection of casting – giving no less than 24 hours notice prior.

SITE VISIT REPORT: 04.04.19

Form work placed in preparation of reinforcement placement which has commenced in areas.

SITE VISIT REPORT: 06.03.19

Works ongoing and form work placement carries on. Bowing observed in certain areas where defective boards were used.

SITE VISIT REPORT: 14.02.19

De-propping of suspended slab ongoing. Props left in key structural locations as advised in method statement.